Ely Modular Housing Project | Route 5 Project Management

Ely Modular Housing Project (78 Properties)

 

Project Overview

Ely was a distressed project owned by Savills Investment Management and constructed as a modular build by Tophat. After Tophat ceased trading in late 2024, Route 5 were appointed as Project Managers and Quantity Surveyors to complete the development.

The modular units were in varying stages of completion, with many internal differences and unfinished civil works. Significant technical civil issues were also inherited on site.


Key Responsibilities

  • Appoint and manage subcontractors to complete the project
  • Resolve all technical issues on site
  • Complete section agreements and planning conditions
  • Issue and control a cost-to-complete plan
  • Programme and oversee the completion of works


Timeline

January 2025

  • Initial site visit and assessment
  • Full audit of outstanding materials
  • Review of technical problems
  • Setup of ongoing design and project meetings

February

  • Start procurement of contractors and materials
  • Liaise with planners, Highways, and Anglian Water
  • Agree civils programme

March

  • Site works paused to arrange insurance
  • Civils delayed due to conflict with mains installed by Tophat
  • Outfall connection issues encountered
  • Main subcontractors appointed

April

  • Delivery of ASHPs and white goods to enable internal works
  • Final subcontractor procurement
  • Service cable/pipeline diversions and road redesign required

May

  • Additional tap and jointing works identified (some plots on-site for 18+ months)
  • Contractors appointed and programme agreed
  • All plots reach watertight status
  • Scaffolding removed

June

  • Painters return to site
  • Joiners begin 3rd fix work
  • Road issues resolved with Highways; civils costs agreed
  • Civil connections still under negotiation


Completion Target

The goal is to complete by the end of October. This is subject to confirmation once road space is booked for the 278 works.

 


Project Images

Take a look at some of the photos we took during our time at the Ely project.

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

Fleckney - Start Day

 


Got a Project You Need Help With?

Whether you're picking up where someone else left off or starting from scratch, we're here to help. Get in touch today to discuss your project.

Enquire Now

Simply fill in the form below and press send and we will get back to you shortly regarding your enquiry.

Our combined expertise offers these guarantees on everything we do.

  • With all our quotes we give a timescale for the work and stick to it.
  • Always available - 8.00-5.30pm five days a week. We return calls within half a day.
  • We give a fixed price for all work.
  • All schemes are commercially reviewed to give options for saving money.
  • We are based in the Midlands to give you nationwide coverage.

Fill out the form below to get in touch with us.

Galliford Try
Countryside
Engie
McCarthy And Stone